Annual Report to shareholders
Released
Released
Announcement PDF
2024 ANNUAL REPORT
1
Contents
Chairman’s Letter .................................................................................................................... 3
Review of Operations .............................................................................................................. 4
Directors' Report……………………………………………………………………………………...16
Corporate Governance Statement ......................................................................................... 29
Directors' declaration ............................................................................................................. 30
Auditor’s Independence Declaration ...................................................................................... 31
Independent Auditor’s Report ................................................................................................ 32
Consolidated Statement of Profit or Loss and Other Comprehensive Income ....................... 36
Consolidated Statement of Financial Position ....................................................................... 37
Consolidated Statement of Changes in Equity ...................................................................... 38
Consolidated Statement of Cash Flows................................................................................. 39
Notes to the consolidated financial statements...................................................................... 40
Consolidated Entity Disclosure Statement ............................................................................. 67
Additional ASX Shareholder Information ............................................................................... 68
Corporate Directory ............................................................................................................... 75
2024 ANNUAL REPORT
2
Chairman’s Letter
Dear Shareholder,
Horizon Gold Limited has made significant advances over the past 12 months with the completion of a
scoping study for the Gum Creek Gold Project. The study includes only the free milling open pittable
portions of the Project’s mineral resources but has returned compelling economic metrics and shows a
clear pathway for delivering value to shareholders.
We’re very pleased with the results of the scoping study and are preparing to commence a feasibility
study and other activities that further enhance the Project’s positive economics on our path to becoming
the region’s next gold producer.
The Company is confident that through further resource drilling, additional shallow oxide gold resources
will be defined at the numerous resource areas not yet included in the scoping study, and that these
will potentially become part of the mine plan, extending the mine life well beyond the 10 years envisaged
in the study.
The granted clearing permit and existing mining proposal should enable a quick transition to mining at
Gum Creek and once established, the new processing facility would become a strategic asset for the
region with the potential to consolidate some of the surrounding stranded gold assets.
The Company continues to hold approximately 60.8 million shares in Alto Metals Limited (ASX:AME)
which currently represents 8.4% of AME’s issued capital. This strategic investment was part of Horizon’s
aim of delivering value to shareholders and advancing the development of the Gum Creek Gold Project,
however, following the proposed merger of AME with Brightstar Resources Limited this investment is
under review.
The Company has established a short-term loan facility with its major shareholder, Zeta Resources
Limited, which will allow Horizon to review its strategic objectives and its funding requirements.
The Board believes that Gum Creek represents a compelling development opportunity, and with gold
at record prices we are confident that our focus on the development of our large gold resource will add
significant value for shareholders.
On behalf of the Board, I would like to thank our non-executive Director Dugald Morrison who recently
resigned for his input and commitment to the Company over the past 4 years, and I would also like to
thank our shareholders for their ongoing support as we look forward to sharing our exciting development
progress during the year ahead.
Yours sincerely
Peter Sullivan
Chairman
2024 ANNUAL REPORT
3
Review of Operations
Horizon Gold Limited (ASX:HRN) (Horizon or the Company) is focused on expanding and enhancing
the quality of its gold resources and unlocking the economic potential of its 100%-owned Gum Creek
Gold Project (Gum Creek or the Project) located in a world class gold province within the Yilgarn Craton
in Western Australia.
Gum Creek has historically produced more than 1 million ounces of gold and hosts a current Mineral
Resource Estimate (MRE) of 2.14 million ounces. The Project covers more than 500km2 of contiguous
tenure over the Gum Creek greenstone belt located within a well-endowed gold region that hosts
multimillion-ounce resources at Mt Magnet, Meekatharra, Wiluna, Bellevue and now at Gum Creek
(Figure 1).
The Project not only represents a significant brownfields exploration opportunity, but also offers
significant greenfields exploration upside along its 80 kilometres of prospective and continuous strike.
All the existing resources and most of the potential resource areas are located on granted Mining
Leases. The Project also has significant infrastructure in place, including a 110-man camp, an operating
airstrip, a relic CIL processing facility, extensive haul road network and a large tailings storage facility.
Figure 1: Gum Creek Gold Project showing surrounding mines and gold deposits over simplified geology.
2024 ANNUAL REPORT
4
Project History
Gold was first discovered in the area at Jonesville (now part of the Swan deposit) in 1926, with the first
recorded gold production in 1931. More modern mining operations commenced in the 1980’s and
ceased in 2005 when the gold price was approximately A$560/oz. To that time, more than one million
ounces of gold was produced from over thirty open pits and three underground mines, with the main
gold-producing areas being Swan-Swift, Kingfisher and Omega.
Unlocking Value at the Gum Creek Gold Project
During the reporting period the Company completed a comprehensive scoping study (Study) that
assessed the recommencement of gold production from near surface, free milling, open pittable gold
resources at the Gum Creek Gold Project 1. The Study returned compelling financial outcomes at a gold
price of A$2,900/oz (approximately A$400/oz below the spot gold price at the time of reporting and
approximately A$600/oz below the spot price as at 30 June 2024), including a pre-tax cashflow of
A$574M, pre-tax NPV8 of approximately A$318M, a pre-tax IRR of 31.5% and a payback period from
commencement of mining of 3.0 years.
The Company considered various options to recommence gold mining at Gum Creek including mining
and toll treating ore at the closest operating gold processing facilities, however the Study confirmed that
constructing and operating a new gravity / CIL processing plant was the optimum business strategy for
the Project.
The Study envisaged an initial mine production target of 24.46Mt @ 1.13g/t Au for 888,000 ounces
(76% Indicated, 24% Inferred) from selected deposits, processed through a new 2.4 million tonne per
annum gravity / CIL processing plant located at the previously permitted Gidgee mill site. There is a low
level of geological confidence associated with Inferred Mineral Resources and there is no certainty that
further exploration work will result in the determination of Indicated Mineral Resources or that the
production target itself will be realised.
Scoping Study Summary
The Study evaluated free milling Whittle in-pit gold resources optimised using a base case gold
price of A$2900/oz (+/- A$200/oz and +/-A$400/oz).
All gold resources in the Study are located on granted mining leases within the 100% owned Gum
Creek Gold Project.
Only deposits with greater than 15,000 gold ounces inside Whittle pit shells from previous pit
optimisation work were included in the Study, which equates to only 14 of the current 26 Gum Creek
Gold Project resource areas.
Ore to be processed through a new 2.4Mt per annum gravity / CIL processing plant located at the
previously permitted Gidgee gold processing site.
Existing Native Vegetation Clearing Permit could be used for clearing the proposed processing
infrastructure area (processing plant), and the Swan, Swift, Eagle and Shiraz deposit areas.
Mining Proposal (ID 46008) is currently approved for the Swift deposit and the Gidgee processing
infrastructure area.
1
Refer to Horizon Gold Ltd ASX Announcement dated 20 March 2024 titled “Compelling Gum Creek Scoping Study”. CP L.Ryan
2024 ANNUAL REPORT
5
Initial open pit mine production target of 24.46Mt @ 1.13g/t Au for 888,000 ounces comprised of
76% Indicated and 24% Inferred Mineral Resources (compliant with the JORC 2012 guidelines).
Average recovered gold production of approximately 84,000oz per year over a 10-year LOM.
LOM C1 cash operating costs of A$1,730/oz produced.
LOM All-in Sustaining Costs (AISC) of A$1,931/oz produced.
Pre-production capital cost of A$238.5M.
LOM sustaining capital cost of A$94.9M.
Compelling financial outcomes at A$2,900/oz gold price:
‒
Pre-tax cashflow of A$574M, pre-tax NPV8 of approximately A$318M, pre-tax IRR of
31.5%, and payback period from commencement of mining of 3.0 years.
Study base case gold price was approximately A$400/oz below the March 2024 spot gold price,
representing significant potential upside to predicted financial outcomes.
The A$3,300/oz gold price scenario returns:
‒
Pre-tax cashflow of A$904M, pre-tax NPV8 of approximately A$548M, pre-tax IRR of
45.8% and payback period from commencement of mining of 2.1 years.
Gum Creek Scoping Study
The Study evaluated free milling Whittle optimised in-pit gold resources from only 14 of the current 26
Gum Creek Gold Project resource areas (refer to Figure 6 below) using a base case gold price of
A$2900/oz. All gold resources used in the Study, including Eagle, Hawk, Heron South, Howards,
Hyperno-Reliance, Kingfisher, Manikato, Shiraz, Snook, Specimen Well, Swan/Swift, Think Big,
Toedter, and Wedge, are located on granted Mining Leases.
Ore is to be processed through a new 2.4Mt per annum gravity / CIL processing plant located at the
previously permitted Gidgee gold processing site using established infrastructure including air strip, haul
roads, tailings dam, waste dumps, in-pit water resources, camp (for construction and overflow
purposes) and existing ROM pads where possible and upgraded where required.
The Study envisaged an average recovered gold production of approximately 84,000oz per year over
a 10-year LOM using an initial open pit mine production target of 24.46Mt @ 1.13g/t Au for 888,000
ounces comprised of 76% Indicated and 24% Inferred Mineral Resources (compliant with the JORC
2012 guidelines) (Table 1).
2024 ANNUAL REPORT
6
Table 1: Scoping Study Open Pit Mine Production Target by Deposit
Deposit
Swan/Swift OC*
Howards*
Eagle
Heron South
Toedter
Hawk
Kingfisher OC
Hyperno-Reliance
Manikato
Shiraz*
Snook
Specimen Well
Think Big
Wedge
Total
Tonnes
10,396,000
8,160,000
1,145,000
907,000
566,000
765,000
256,000
328,000
335,000
491,000
158,000
252,000
431,000
274,000
24,463,000
Production Target
Au (g/t)
1.29
0.85
1.08
1.17
1.48
1.09
2.11
1.25
1.20
0.81
1.83
1.52
1.06
1.65
1.13
Ounces
431,000
222,000
40,000
34,000
27,000
27,000
17,000
13,000
13,000
13,000
9,000
12,000
15,000
15,000
888,000
* MIK models constructed as diluted mining models, hence no further mining dilution or mining recovery factors have been applied.
Notes: Figures have been rounded. The Whittle optimisation work in this Study used the mineral resource estimates referred to in previous
Horizon Gold Limited ASX announcements titled “Gum Creek Gold Project Resource Update” dated 12 February 2021, “32% Increase in
Resources at Gum Creek Gold Project” dated 25 July 2022 and “19% Increase in Gold Resources at Gum Creek Gold Project” dated 15
May 2023, all of which are available to view at https://horizongold.com.au/announcements/.
The estimated pre-production capital cost of A$238.5M includes existing plant demolition and
removal, a new 2.4Mt per annum gravity / CIL processing plant, a new 200-person camp, pit dewatering
costs, and a 20% contingency. Pre-production mining costs (open pit pre-strip) of A$36.4M are included
in the mine operating costs over the first 5 months of operations.
Sustaining capital includes all capital expenditure post-production commencement. Sustaining capital
for the processing plant includes allocation of capital replacements and throughput optimisation, as well
as the construction of a second tailings storage facility (Table 2).
2024 ANNUAL REPORT
7
Table 2: Summary of Capital Expenditure
Pre-Production Capital
Demolition of existing Processing Plant
Processing Facilities (incl. offices)*
Camp and Site Facilities
Property Plant & Equipment (incl. vehicles and administration offices)
Tailings Storage Facility (TSF)*
Open Pit Dewatering (pumps, pipes, and operating costs incl. diesel)
Pre-production Mining Contractor Costs**
Total Pre-production Capital
Sustaining Capital (LOM)
Tailings Storage Facility (TSF)
Dewatering & Water Management (pumps, pipes, vehicles & equipment)
Property Plant & Equipment (vehicle & building maintenance)
Total Sustaining Capital
Total Capital Costs
(A$M)
1.0
193.1
25.4
3.0
3.5
10.5
2.0
238.5
(A$M)
30.1
62.8
2.0
94.9
333.4
* Costs are expected to be accurate within the study allowance of ±35%, the estimates include a contingency allowance of 20%.
** Pre-production mining costs of $36.4M in addition to mining contractor costs are included in mine operating costs over the first 5 months.
LOM C1 cash operating costs of A$1,730/oz (produced), include Mining costs (A$34.30/t milled,
A$993.6/oz produced), Processing costs (A$23.61/t milled, A$684.1/oz produced) and General and
Administration (G&A) costs (A$1.82/t milled, A$52.7/oz produced). LOM All-in Sustaining Costs
(AISC) of A$1,931/oz (produced), include Sustaining Capital costs (A$3.88/t milled, A$112.4/oz
produced) and Royalties (Govt & 3rd party) (A$3.05/t milled, A$88.4/oz produced) (Table 3). It is
estimated that approximately A$13.4M in royalties will be paid to third party companies, and
approximately A$61.2M in royalties will be paid to the State Government over the LOM.
Table 3: Estimated Operating Costs
Operating Cost Description
Mining (incl. grade control, haulage, dewatering)
Processing
Site G&A
C1 Cash Operating Cost*
Royalties
Sustaining Capital
All-in Sustaining Cost (AISC)**
LOM Operating Cost (A$M)
838.9
577.6
44.5
1,461.0
74.6
94.9
1,630.5
A$/t milled
34.30
23.61
1.82
59.73
3.05
3.88
66.66
$/oz Au Produced
$993.6
684.1
52.7
1,730.40
88.4
112.4
1,931.20
* C1 cash cost includes mining, processing, and administration costs.
** AISC per ounce payable includes C1 cash cost, royalties and sustaining capital. It does not include corporate, exploration or non-sustaining
costs.
A range of scenarios considering different production profiles and cut-off grades were evaluated in the
Study. The 2.4 Mtpa throughput sustains full production for ten years, is the preferred production rate,
and provides the opportunity to add additional satellite deposits beyond the current mining schedule.
The Study demonstrated that the recommencement of open pit mining at a base case gold price of
A$2,900/oz provides a substantial economic return, yielding a pre-tax cashflow of A$574M, pre-tax
NPV8 of approximately A$318M, and a pre-tax IRR of 31.5%. The payback period from
commencement of mining in this scenario would be 3.0 years. The annual undiscounted cashflow and
cumulative undiscounted cashflow (from funding drawdown) outcomes are presented in Figure 2 below.
2024 ANNUAL REPORT
8
Cashflow
$700
$600
$500
$400
$300
$200
$100
$$(100)
0
1
2
3
4
5
6
7
8
9
10
11
$(200)
$(300)
Cashflow
Cumulative Cashflow
Figure 2: Cashflow and Cumulative Cashflow (A$M) by Year
The Study base case gold price retains a significant potential upside to predicted financial outcomes
with the A$3,300/oz gold price scenario returning a pre-tax cashflow of A$904M, pre-tax NPV8 of
approximately A$548M, pre-tax IRR of 45.8% and a payback period from commencement of
mining of 2.1 years (Table 4).
Table 4: Scoping Study – Gold Price Scenarios
Description
Pre-tax Cashflow (A$M)
NPV8 (A$M)
IRR (%)
Payback Period (years)
$2,500
$244.96
$88.09
15.3%
4.6
$2,700
$409.59
$202.94
23.8%
3.7
Gold Price (A$/oz)
$2,900*
$574.23
$317.79
31.5%
3.0
$3,100
$738.87
$432.65
38.8%
2.5
$3,300
$903.50
$547.50
45.8%
2.1
* Base case gold price
A sensitivity analysis of the Study’s key economic parameters demonstrated that Project economics are
most sensitive to a change in gold price, followed by a change in operating costs, discount rate and
capital expenditure. The results of the sensitivity analysis are presented in Figure 3 in terms of NPV
sensitivity.
2024 ANNUAL REPORT
9
Figure 3: Study NPV Sensitivity Analysis
The Company’s strategy is to mine larger, lower risk open pit deposits adjacent to the proposed
processing area that return substantial profit margins in the first 5 years of mining. Initially, this includes
the Swan/Swift deposit, with other “Central” satellite pits introduced during the 3rd year of mining (Eagle,
Wedge, Hawk and Kingfisher). Due to higher strip ratios, from year 6 the “Northern” satellite pits (Shiraz,
Snook, Specimen Well and Toedter) and “Southern” satellite pits (Hyperno Reliance, Heron South,
Manikato and Think Big) will be mined while the 2 haul truck fleets remain on site (Figure 4). Howards
will be mined from year 7 to 10 using a single mining fleet.
Quarterly Production (tonnes) by Mining Location
5,000,000
4,000,000
3,000,000
2,000,000
1,000,000
-
0
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44
SwanSwift1
SwanSwift2
SwanSwift3
SwanSwift4
Howards1
Howards2
Howards3
Eagle
Wedge
Hawk
Kingfisher
Shiraz
Snook
Specimen Well
Toedter
Hyperno Reliance
Heron South
Manikato
Think Big
Figure 4: Quarterly Production Schedule by Deposit
2024 ANNUAL REPORT
10
Scheduled ore mined (million tonnes per annum) by resource category and average gold grade (g/t) is
presented in Figure 5 below.
Mined Ore (Mt)
3.0
2.5
2.0
1.46
2.22
1.15
1.5
2.26
2.03
1.97
2.07
2.04
1.75
1.0
1.34
1.15
0.5
0.0
1.02
1.18
0.75
-
1
0.10
0.17
2
3
0.39
0.47
4
5
0.21
INFERRED
6
7
INDICATED
8
9
0.34
0.27
10
11
0.14
12
Avg Grade
Figure 5: Annual Ore Mined (Mtpa) by Resource Category and Average Gold Grade (g/t)
Existing granted clearing and mining proposals should enable a quick transition to mining at Gum Creek
and once established, the processing facility will become a strategic asset for the region with the
potential to consolidate some of the surrounding stranded gold assets.
The Scoping Study provides justification that the development of the Gum Creek Gold Project is a
commercially viable stand‐alone mining operation and accordingly the Board of Horizon Gold Limited
are supporting the commencement of a Feasibility Study.
The Study retains significant upside including excellent potential to extend the proposed mine life
through underground mining and other processing methods. Underground mining options at all deposits
including Swan/Swift, Kingfisher, Omega and Wilsons are yet to be evaluated, and additional shallow
resource expansion drilling could potentially increase the resource size and gold grade of the 12
resource areas not included in the study and elevate them to an economically viable status for inclusion
into the mining schedule.
2024 ANNUAL REPORT
11
Gum Creek Future Work and Growth Potential
Since completing the Study, further work on improving the economic outcomes of the Gum Creek
Project has been undertaken with a focus on reducing pre-production capital expenditure, including
processing facility and sustaining capital cost reductions. Deposits with lower strip ratios have also been
brought forward in the mining schedule to reduce initial pre-strip mining and water management related
capital costs.
Geological modelling and wireframing of the Swan/Swift open cut, Howards and Shiraz gold
mineralisation has been completed in advance of converting the Multiple Indicated Kriging (MIK)
resource models to Ordinary Kriging (OK) resource models which better represent the style of
mineralisation at the deposits, and further evaluation of different grade cutoff options and processing
throughput rates has commenced.
Drilling planned over the next 12 months will include resource drilling targeting shallow oxide resources
near the Gidgee mill and at strategic locations along the existing haul road. Limited infill resource drilling
to cover additional geotechnical and metallurgical requirements is also planned. The drilling will aim to
further increase the mineral resource inventory and support the current economic studies at the highly
prospective Gum Creek Project.
Wide-spaced drilling is also planned to explore the extensive untested strike of known mineralised
structures in the Gum Creek Project and further advance the large pipeline of regional gold targets
within this underexplored, highly strategic asset.
2024 ANNUAL REPORT
12
Gum Creek Gold Resource Estimate
On 15 May 2023 the Company announced an updated Mineral Resource Estimate (MRE) for the Gum
Creek Gold Project of 44.45Mt @ 1.50g/t Au for 2.14 million ounces contained gold reported in
accordance with the JORC Code (2012 Edition) and based on documentation prepared by Competent
Persons as defined by the JORC Code guidelines. A summary of the current MRE is detailed in Table
5 below.
Table 5: Gum Creek Gold Resources as at 15 May 2023
Cut-off
grade
(g/t Au)
Resource
Date
Swan/Swift OC
Swan UG
Swift UG
Wilsons UG
Howards
Kingfisher OC
Kingfisher UG
Heron
Heron South
Shiraz
Eagle
Wyooda
Snook
Hawk
Toedter
Specimen Well
Wedge
Camel Bore
Kearrys
Psi
HypernoReliance
Melbourne
Bitter
Deep
South
Reliance
Eagles Peak
Orion
Wahoo
Fangio
Jul-22
Jul-22
Jul-22
Jul-13
May-23
May-23
May-23
May-23
May-23
May-23
May-23
Jul-22
Jul-22
May-23
Aug-16
May-23
May-23
Jul-22
May-23
Jul-22
0.4
2.5 / 3.0*
3.0
1.0
0.4
0.6
1.5
0.6
0.8
0.4
0.8
0.8
0.8
0.6
0.5
0.8
0.6
0.8
0.6
0.8
May-23
Total
Indicated
Au
Tonnes
Gold (oz)
(g/t)
Tonnes
9,980,000
301,000
2,131,000
8,064,000
621,000
359,000
330,000
720,000
2,539,000
395,000
430,000
75,000
378,000
379,000
450,000
100,000
1.09
6.91
5.33
0.82
1.77
3.48
2.11
1.79
0.70
1.94
1.56
2.57
1.28
1.47
1.24
2.08
349,500
66,900
365,000
213,100
35,400
40,200
22,400
41,400
57,300
24,700
21,600
6,200
15,500
17,900
18,000
6,700
2,735,000
226,000
138,000
136,000
2,136,000
269,000
917,000
1,822,000
761,000
1,064,000
764,000
862,000
846,000
471,000
689,000
529,000
487,000
100,000
46,000
226,000
0.6
119,000
1.73
6,600
May-23
0.6
214,000
1.56
May-23
0.6
176,000
May-23
Jul-22
Jul-22
May-23
0.6
0.8
0.8
0.6
264,000
69,000
99,000
28,193,000
Inferred
Au
Gold (oz)
(g/t)
Tonnes
434,100
118,500
25,400
391,000
266,900
45,100
135,700
110,600
78,900
78,900
68,800
64,800
54,000
34,400
34,000
25,500
23,800
21,800
20,000
19,000
445,000
1.31
18,800
6,100
362,000
1.44
16,800
1.56
2,400
224,000
1.62
11,700
0.99
1.40
1.25
1.35
1,300
8,200
10,400
1,300
305,000
251,000
258,000
129,000
1.16
1.43
1.25
1.33
11,400
11,500
10,400
5,500
84,600
51,600
25,400
26,000
53,800
9,700
95,500
88,200
37,500
21,600
44,100
43,200
47,800
18,900
34,000
25,500
23,800
3,900
2,000
12,300
12,715,000
527,000
138,000
2,267,000
10,200,000
890,000
1,276,000
2,152,000
1,481,000
3,603,000
1,159,000
1,292,000
921,000
849,000
689,000
529,000
487,000
479,000
496,000
326,000
326,000
1.16
12,200
10,700
148,000
1.28
1.64
9,300
48,000
1.19
1.49
1.32
10,100
3,300
4,200
41,000
182,000
258,000
30,000
1,346,000
16,257,000
Gold (oz)
1.06
6.99
5.72
5.36
0.81
1.58
3.31
1.60
1.66
0.68
1.85
1.56
1.82
1.26
1.54
1.50
1.52
1.42
1.25
1.81
0.96
7.10
5.72
5.95
0.78
1.12
3.24
1.51
1.53
0.63
1.80
1.56
1.76
1.25
1.54
1.50
1.52
1.21
1.35
1.69
1.48
Total
Au
(g/t)
1.51
791,300
44,450,000
1.50
2,137,300
* Cut-off grades are 2.5g/t Au for Swan Underground (UG) Indicated, and 3.0g/t Au for Swan UG Inferred.
** Wyooda includes the Kingston Town, Think Big and Manikato resources which are within 600m and 200m of each other respectively.
Notes: Figures have been rounded.
The information in this announcement that relates to the reporting of the Wilsons, and Toedter Mineral Resources has been extracted from
the Horizon Gold Limited ASX announcement titled “Gum Creek Gold Project Resource Update” dated 12 February 2021 and is available
to view on https://horizongold.com.au. The information in this announcement that relates to the reporting of the Swan/Swift Open Pit Mineral
Resource, the Swan and Swift Underground Mineral Resource and the Camel Bore, Orion, Psi, Snook, Wahoo and Wyooda Mineral
Resources has been extracted from the Horizon Gold Limited ASX announcement titled “32% Increase in Resources at Gum Creek Gold
Project” dated 25 July 2022 and is available to view on https://horizongold.com.au.
2024 ANNUAL REPORT
13
Gum Creek Base Metal Resource Estimate
On 14 March 2023 the Company announced a maiden MRE of 7.0 Mt @ 1.8% Zn, 0.5% Cu, 5.0g/t Ag
(2.9% ZnEq) at a 2.0% ZnEq cut-off for 200,000 ZnEq tonnes (130,000t Zn, 30,000t Cu, 1.1Moz Ag)
for the Altair Zinc-Copper-Silver deposit located 24 kilometres to the north-northwest of the Gidgee Mill
(Figure 6, and Table 6).
Table 6: Altair Inferred Mineral Resource as at 14 March 2023 (Zinc Equivalent % cut off)
Cut-off
Total Tonnes & Grade
Total Metal Content
ZnEq %
Mt
ZnEq %
Zn %
Cu %
Ag g/t
ZnEq (Kt)
Zn (Kt)
Cu (Kt)
Ag (Moz)
1.5
11.9
2.3
1.5
0.3
4.5
270
180
40
1.7
2.0
7.0
2.9
1.8
0.5
5.0
200
130
30
1.1
2.5
4.3
3.3
2.1
0.5
5.4
140
90
20
0.8
Note: The metal equivalent calculation formula is ZnEq % = Zn (%) + 2.78 x Cu (%) + 0.018 x Ag (g/t) using metal prices of A$4,500/t Zn,
A$12,500/t Cu and A$30/oz Ag. Based on preliminary metallurgical studies, recoveries used were 90% for Zn, 90% for Cu, and 75% for
Ag. In Horizon’s opinion all elements included in the metal equivalents calculation have a reasonable potential to be recovered and sold.
Figures have been rounded.
Figure 6: Gum Creek Gold Project current mineral resources and exploration targets over regional
geology.
2024 ANNUAL REPORT
14
Corporate
Alto Metals Limited Share Purchase
In July 2023 the Company acquired 60.8 million shares in Alto Metals Limited (ASX:AME) for $3.17
million which currently represents 8.4% of AME’s issued capital. The average price paid per AME share
was $0.052. This strategic investment is part of Horizon’s broader aim of enhancing the value of the
Gum Creek Gold Project.
AME owns the Sandstone Gold Project located approximately 90km south of the Gidgee mill. The
Sandstone Gold Project covers over 740km2 of the Sandstone Greenstone Belt and contains an
unconstrained MRE of 23.5Mt @ 1.4g/t Au for 1.05Moz.
On 1 August 2024, Brightstar Resources Limited (ASX:BTR) and AME announced they had entered
into a Scheme Implementation Deed under which AME agreed to propose a Scheme of Arrangement
for the acquisition of 100% of AME by BTR. The transaction has an implied value of approximately 6
cents per AME share and the AME share price has subsequently increased to similar levels from 3.4
cents at 30 June 2024 and the value reflected in the Financial Statements. This investment is under
review.
Renounceable Entitlement Issue
On 4 October 2023, the Company announced a 1 for 5 Renounceable Entitlement Issue (“the Issue”)
at $0.30 per share, to raise approximately $7,500,000. The Company received acceptances for
$5,897,485 in respect to 19,658,282 shares, representing a 79% take up of the Issue. As part of the
Application and Issue process the Company also repaid in full (through offset) the short-term loans
mentioned below (including interest) to the value of $4,059,028 to the subsidiary company of Horizon’s
major shareholder, Zeta Resources Limited. As such net proceeds from the Entitlement issue after
repayment of the loan and interest was $1,838,457 before costs.
Funding
In June 2023 Horizon secured a short-term funding facility of up to $500,000 from Zeta Energy Pte
Limited (a wholly owned subsidiary of Horizon’s major shareholder Zeta Resources Limited). In July
2023, an additional facility of $3,180,000 was secured for the purchase of AME shares and another
facility of $300,000 was secured to provide extra working capital. The loan facilities were unsecured,
could be drawn in tranches of not less than $50,000 and interest was payable at 8.0% per annum. The
funds were repayable by no earlier than 31 December 2023.
The above short-term funding was repaid in full in November 2023 as part of the application and issue
process of the Renounceable Rights Issue.
In May 2024 Horizon secured a short-term funding facility of up to $1,000,000 from Zeta Energy Pte
Limited (a wholly owned subsidiary of Horizon’s major shareholder Zeta Resources Limited). The loan
facility is unsecured, could be drawn in tranches of not less than $50,000 and interest is payable at
8.0% per annum. The funds are repayable by no earlier than 31 December 2024. At 30 June 2024 no
drawdown on the facility has been made but subsequent to financial year end $800,000 of the facility
has been drawn down. In September 2024 Zeta Resources Limited agreed to increase the short-term
loan facility to $1,500,000.
.
2024 ANNUAL REPORT
15
Directors’ Report
30 June 2024
The directors present the